Once the Adding New GCS900 Machines to WorksManager section has been completed, please refer to the below for Project syncing. Note: the device will need to be added to an active project inside WorksManager before completing these steps.
1. select the Menu Button
2. Select the Installation soft key
3. Select Connectivity Settings using the D-pad and select OK
4. Now select Wireless Data Sync and hit OK
5. Select the Start soft key to commence the data sync from WorksManager
6. This will now show a progress bar and you will see the associated files being transferred. Once Complete the below screen will appear, select Exit to exit the menu.
The files will now be available in the Designs menu.